Experience across every major infrastructure mode

Selected credentials from the prior roles of Devstrat's leadership with Indian Railways, DMRC, RITES, BMRCL, RVNL, NCRTC and Rodic Consultants — shown to evidence domain depth. Open any project for photos, facts and the role performed.

Prior-role experience. The projects and credentials presented represent the professional experience of Devstrat's leadership in previous roles. They are not represented as projects executed by Devstrat Private Limited.

Selected credentials

12 credentials

Viewers' gallery at Rajiv Chowk, an underground interchange on the Yellow Line (Line 2). MetroTunnels

Delhi Metro Phase I, Line 2 (underground)

  • ~11 km · Underground length
  • 10 · Underground stations, plus depot
  • 8–9 months · Commissioned ahead of schedule
RoleConcept to commissioning View project
Airport Express train on the elevated section above a Delhi road. MetroTunnels

Delhi Airport Express Line

  • ~11 km · Bored, NATM and cut-and-cover tunnels
  • 4 · Underground stations
  • ₹1,480 Cr+ · Underground works supervised
RoleChief Resident Engineer View project
Baiyappanahalli station, the eastern end of Reach 1. MetroViaduct

Bangalore Metro Reach 1

  • 5.5 km · Viaduct
  • 6 · Stations
  • 2 · Depots
RoleDetailed design View project
Underground platform at Esplanade station, Kolkata Metro. Metro

Kolkata Metro extensions

  • ~66 km · Surface, elevated and underground
  • 47 · Stations
  • 3 · Depots
RoleLeadership with RVNL View project
Namo Bharat train at Meerut South RRTS station. RRTS

Delhi–Alwar & Delhi–Panipat RRTS

  • ~107 km · Delhi–Alwar corridor
  • ~103 km · Delhi–Panipat corridor
  • 31 · Stations, 8 underground
RoleTechnical Head – Planning, Design & Execution View project
Mangroves on the eastern shore of Thane Creek. High-speed railTunnels

Mumbai–Ahmedabad High-Speed Rail

  • ~21 km · BKC–Shilphata tunnel section
  • ~7 km · Beneath Thane Creek
  • 13.6 m · TBM cutterhead diameter
RoleFeasibility & DPR View project
The completed arch across the Chenab gorge. RailwaysBridges

Chenab Bridge, USBRL

  • 1,315 m · Total length
  • 467 m · Arch span
  • ~359 m · Above the river bed
RoleDesign review View project
Approach road and portal building at the Atal Tunnel. TunnelsHighways

Atal Tunnel, Rohtang

  • 9.02 km · Tunnel length
  • ~3,000 m · Altitude
  • 46 km · Route saving
RoleAdvisor to BRO, nominated by DMRC View project
Bathinda Junction, at one end of the doubled section. Railways

Rajpura–Bhatinda doubling

  • 172.6 km · Railway doubling
RoleLeadership with RVNL View project
A Rajdhani Express at New Delhi. Railways

Indian Railways — Rajdhani routes & yard remodelling

  • 1989 · IRSE batch
  • 1998–99 · Best Performance Shield — a first for Eastern Railway
RoleIRSE, 1989 batch View project
Pir Panjal railway tunnel on the USBRL. RailwaysHill terrain

Himalayan & hill railways

  • NATM · Himalayan tunnel design, USBRL
  • Hill terrain · Railway structures, NF Railway
RoleStructures & tunnel design View project
Eight-lane Delhi–Gurgaon expressway on National Highway 8. Highways

Highways, Bridges & Tunnels — Rodic Consultants

  • 2023–26 · Business Head, Highways, Bridges & Tunnels
RoleBusiness Head View project

Discuss your infrastructure project

Tell us about the asset and the stage it is at — feasibility, DPR, design review, construction support or monitoring. We will set up a scoping discussion with the right engineers.